FTA gives permission to begin final design.
-
MTA board accepts findings of real estate public hearing,
giving green light for property acquisition.
-
Noise and vibration testing is completed.
-
Construction contract for Arch Street Yard is awarded.
-
Noise mitigation measures are completed at Newcomers High
School in Queens.
-
Switch exchange machines are purchased.
-
Queens construction office opens.
-
Construction begins on Queens access shaft at existing
bellmouth of 63rd Street Tunnel.
-
Contract is awarded to demolish Superior Reed Building
and prepare Rail Yard A in Queens.
-
Contract is awarded for East Yard Environmental Remediation.
-
FTA issues Letter of No Prejudice to allow construction
to move forward on the Queens open-cut excavation, the Manhattan
tunnels, the demolition of 47 E. 44th Street, and Wood Interlocking.