Project Description
|
|||
|---|---|---|---|
The Second Avenue Subway will be New York City’s first major expansion of the subway system in over 50 years. When fully completed, the line will stretch 8.5 miles along the length of Manhattan's East Side, from 125th Street in Harlem to Hanover Square in Lower Manhattan. In addition, a track connection to the existing 63rd Street and Broadway Lines, will allow a second subway line to provide direct service from East Harlem and the Upper East Side to West Midtown via the Broadway express tracks. |
|||
| Construction Phasing | |||
Station |
Subway Lines |
Transfers |
Location of |
125 St-Lexington Av |
|
|
Lexington Av at 125 St |
116 St-2 Av |
|
- |
116 St at 2 Av |
106 St-2 Av |
|
- |
108 St at 2 Av |
96 St-2 Av |
|
- |
96 St at 2 Av |
86 St-2 Av |
|
- |
86 St at 2 Av |
72 St-2 Av |
|
- |
72 St at 2 Av |
Lexington Av-63 St |
|
|
Lexington Av at 63 St |
55 St-2 Av |
|
|
55 St at 2 Av |
42 St-2 Av |
|
|
44 St at 2 Av |
34 St-2 Av |
|
- |
34 St at 2 Av |
23 St-2 Av |
|
- |
26 St at 2 Av |
14 St-2 Av |
|
|
14 St at 2 Av |
Houston St-2 Av |
|
|
3 St at 2 Av |
Grand St-Chrystie St |
|
|
Grand St at Chrystie St |
Chatham Square |
|
- |
East Broadway at Bowery |
Seaport |
|
- |
Fulton St at Water St |
Hanover Square |
|
- |
Wall St at Water St |
(* Specific station entrances and subway transfer points are under evaluation and are subject to change as station design progresses)
All of the stations will have escalator and elevator access including access for the disabled, and will feature climate control features to maximize customer comfort.
| The Second Avenue Subway is being planned in four phases. The four phases, which could potentially overlap, are as follows: | |||
Phase 1: Construction will occur from 105th Street to 72nd Street, including the tunnel connection to the 63rd Street/Broadway Line, and will use an existing tunnel section from 99th-105th Sts; subway service will operate from 96th Street to West Midtown Manhattan and Brooklyn via the Broadway Line.
When completed, service on Phase One will be provided by an extension of the |
SAS Phase One Map |
||
Phase 2: Construction will occur from 125th Street to 105th Street, including the utilization of an existing subway tunnel section from 110th – 120th Streets; subway service will be provided from 125th Street to West Midtown Manhattan and Brooklyn via a further extension of the |
|||
Phase 3: Construction will occur from 72nd Street to Houston Street; subway service will continue to be provided by the |
|||
Phase 4: Construction will occur from Houston Street to Hanover Square; subway service will continue to be provided by the
|
|||
|
|||