Schedule
- $138M Committed to Expedite Double Track
May 2012
- Phase I - Awarded Design/Environmental Contract
July 2012
- Phase I - Design/Build Award and Construction
November 2013 - September 2016
- Phase II - Preliminary Design
January 2015 - September 2015
- Phase II - Design/Build Award and Construction
April 2016 - December 2018