Video of Work to Rebuild Montague Tubes Now on YouTube

Montague Tubes
Work on post-Sandy Montague tubes

A video of the ongoing work to rebuild the Montague Tubes is now available on the MTA’s YouTube page.

The scope of work for the Montague Tubes is extensive, amounting to a near rebuilding of the link which connects Downtown Brooklyn with Lower Manhattan.  The work will be completed in two contracts.  The first; repair of all right-of-way components includes significant work to tracks, tunnel lighting, circuit breaker houses, power substations, pump rooms, fan plant, power cable and ducts.  The second contract will repair of signal equipment.  Work for both contracts will occur while the tube is shut down for a period of 14 months.

You can view the video on the MTA’s YouTube page: http://youtu.be/rwXFjunqEAs.  Go to http://youtu.be/-KWFo5x2hK8 to view a video of the Tubes before rebuilding efforts commenced.